Turn-Key Lump Sum project including performance guarantee, 22 months’ time frame, to provide an isomerization plant in Croatia.
- 160,000 EPCM hours.
- 40 P&ID’s.
- 2000 Activities on the Gant.
- 45 Km piping.
- 800 Ton, steel construction.
- 3D modeling for the entire design.
- 1800 I/O connected to process computer.
- 60 pieces of static equipment, 40 large scale pumps, 4 compressors, 3 heaters total of 123 units delivered to site.