The Challenge:
Revamp the 4 following treatment lines
Mineral Oil Line
Vegetable Oil Line
Process water line
The Solution:
Galil was awarded first with a technological survey which followed by a TK project with the following stages :
Process water line- A physico chemical treatment followed by a bio plant
Mineral Oil Line-A Di Canter separation followed by A high speed separator
Vegetable Oil Line A Di Canter separation followed by A high speed separator
The total budget of the initial project was $3 million.