ECO oil- Industrial wastewater treatment plant

The Challenge:

Revamp the 4 following treatment lines

Mineral Oil Line

Vegetable Oil Line

Process water line

The Solution:

Galil was awarded first with a technological survey which followed by a TK project with the following stages :

Process water line- A physico  chemical treatment followed by a bio plant

Mineral Oil Line-A Di Canter separation followed by A high speed separator

Vegetable Oil Line A Di Canter separation followed by A high speed separator

The total budget of the initial project was $3 million.

 